This project involved a full replacement of aging stormwater infrastructure along Martin Alley in Evans City Borough. It targeted a residential area north of Main Street (PA Route 68) that experiences chronic drainage issues during rain events. Project limits were set within the public right-of-way to minimize impacts on private property and utility services. In the fall of 2024, Evans City commissioned State Pipe Services, Inc. to perform exploratory camera work along Martin Alley. Video revealed a failing stormwater outfall, deteriorated subsurface vitrified clay pipes, and undersized catch basins resulting in reduced flow capacity, surface stormwater pooling, and frequent maintenance issues that burden both residents and municipal maintenance crews. As part of this exploratory work, a major tree root intrusion was identified and cleared, providing some immediate short-term drainage relief. In addition, an illicit sanitary sewer lateral connection was found and subsequently rerouted by the ECWSA (at their expense).


Analysis of the camera work supported the design of a modern storm drain system. A 2024 initial design for the segment between Breakneck Creek and North Washington Street was supplemented in early 2025 to include the entire Martin Alley corridor, to a point just east of North Jackson Street. Herbert, Rowland & Grubic, Inc. (HRG) performed the engineering design work. It included 700 linear feet (LF) of 24” diameter, 145 LF of 18” diameter, and 52 LF of 15” diameter smooth-lined corrugated plastic pipe (SLCPP); 14 new catch basins; four (4) manholes; and a backflow preventer to minimize flooding in the surrounding residential areas. It also included a concrete headwall with a rip-rap apron at the outfall for pipe protection. Much of the Martin Alley surface was repaved upon the project’s completion.
The project was bid and awarded to Terra Works in May 2025; final construction cost was $344,866. In addition, the Borough requested a change order that included the replacement of a collapsing catch basin near where Evans Street meets Route 68 ($22,110). A second illicit sanitary lateral was identified at this location and rerouted by ECWSA. Construction was completed in January 2026. Subsequently, as-built drawings were produced and storm sewer data was incorporated into the Borough’s Geographic Information System (GIS).


Project Financials
SBSA provided financial assistance for this stormwater project by reimbursing Evans City Borough for engineering expenses incurred prior to (and ineligible for) their 2024 DCED LSA grant award, equivalent to about 3.9% of the overall project cost.